The Daily Grind Drive-Thru ·10 open gates · 10 in register (T-01–T-10)
| Gate | Finding | Severity | Type | Requirement | Status | Tags |
|---|---|---|---|---|---|---|
| T-01 | Generator diesel refueling labor for temporary power duration | high | uncovered mandatory scope | REQ-TEMP-FUEL | open | BLOCKING |
| T-02 | Drive-thru window perimeter flashing and weatherproofing | high | uncovered mandatory scope | REQ-FLASH-DTW | open | BLOCKINGAGENT-FOUND |
| T-03 | Site drainage cleanouts per civil scope register | high | uncovered mandatory scope | REQ-DRAIN-CO | open | BLOCKING |
| T-04 | Owner-furnished walk-in cooler rigging and set (OFCI) | high | ofci unassigned | REQ-OFCI-COOLER | open | BLOCKINGENGINE-FLAGGED |
| T-06 | Addendum #2 exterior soffit LED allowance | high | addendum not in bids | REQ-ADDENDUM-LIGHTING | open | BLOCKINGADDENDUM PENDING |
| T-07 | Line-level low bids use different vendors; compliant award must pick one contractor across the bundle. | high | bundle split violation | — | open | BLOCKINGENGINE-CALCULATED |
| T-09 | Paving quantity basis 1200 SY per civil takeoff | high | quantity basis mismatch | REQ-PAVING-QTY | open | BLOCKINGENGINE-FLAGGED |
| T-10 | Bid security / surety bond per Division 00 | high | uncovered mandatory scope | REQ-BID-SEC | open | BLOCKING |
| T-05 | Leveling must use latest revision amounts only. | medium | bid revision superseded | — | open | ENGINE-FLAGGEDFOR AWARENESS |
| T-08 | Raw low steel pick violates schedule; use schedule_feasible scenario. | medium | schedule lead exceeded | — | open | ENGINE-CALCULATEDFOR AWARENESS |